Once all cabinets are in, countertops are either installed immediately following or templated for cutting offsite. Offsite fabrication of coutertops varies based on the coutertop material and demand.
TYPICAL Lead Times for Countertop Installation (After Final Template):
- Laminate: installed along with cabinets
- Cultured Marble: installed along with cabinets
- Quartz: 2-3 weeks
- Granite: 2-3 weeks
- Solid Surface: 2-3 weeks
- Quartzite *varies - based on individual slabs